Grassed waterways for managing surface water in Western Australia

Page last updated: Thursday, 30 June 2022 - 11:59am

Please note: This content may be out of date and is currently under review.

Natural or constructed grassed waterways can be used to safely move surface water across the landscape, handle water flow into and out of dams, the end of grade banks and other surface water disposal structures.

The Department of Primary Industries and Regional Development recommends that grassed waterways are part of a whole farm water and salinity management program.

The information in this page is only a guide – seek expert advice before planning, and use expert contractors for construction where necessary. Each landholder has a duty of care to make sure that flows from earthworks are not discharged indiscriminately on a neighbouring property and that stream flows are not significantly diminished or degraded.

See Conservation earthworks legal requirements of landholders for more information.

Why use grassed waterways?

Natural or well constructed grassed waterways provide an effective and cost-efficient way of safely moving surface water from the ends of grade banks, diversions, into dams, dam overflows or other water concentrations to a stable discharge point. These structures greatly reduce the risks of erosion and flooding.

Conditions and considerations

Where grassed waterways can be used

  • all sites that can be modified by increasing the water capacity and/or adding vegetation cover – using this practice alone or combined with other conservation practices
  • where overland flows lead to first order streams – first and second order streams may be reconstructed to increase capacity and stability
  • where levees can be constructed on streams of first and second order
  • on large catchments and for streams larger than second order, if people with appropriate stream engineering skills undertake design and construction.

Where surface water is being collected and stored in dams, we recommend roaded catchments instead of grassed waterways. Roaded catchments have a much lower runoff threshold.

Planning considerations

  • Grassed waterways are planned to discharge into first order streams. Discharging into streams of greater order must not interfere with stream flood peak flows or damage the stream banks.
  • Identify any services likely to be affected by the construction of planned works. Discuss the plans with the service provider to confirm ways of avoiding any disturbance or damage.
  • The critical time to install a grassed waterway is when vegetation cover is being established.
  • Species selected for vegetation cover should be appropriate and able to endure the range of operating conditions:
    • form dense groundcover with few gaps
    • not form clumps or barriers to water movement
    • generally less than 20 cm tall
    • selfseeding
    • suit the soil, water conditions and climate.
  • Waterways are to be fenced on both sides of the channel or outside of levees, leaving adequate room for maintenance machinery.
  • Provide livestock and vehicular crossings as necessary to prevent damage to the waterway and its vegetation.
  • If trees and shrubs are to be incorporated, they should not be planted in the waterway channel.
  • Bends should be avoided. Where this is not practical, they must not be acute as this places undue hydraulic stress on retaining banks and waterway surface. Sharp bends may make fencing difficult.

Back to top

Design criteria

Site characteristics are accurately measured.

Soil types – at the construction site are determined and tested to ensure the stability of the proposed structure.

Channel slope – can be on any slope or combination of slopes up to 10%.

Catchment run-off peak flow – to be determined by a recognised method, such as the Flood Index Method or the Rational Method.

Channel cross-sectional shape – is trapezoidal or parabolic in shape (Figure 1). Sideslope ratio of waterway bank to be no steeper than 2:1.

Diagram of cross-sections of grassed water ways with a trapezoidal or parabolic base.
Figure 1 Typical cross-sections for a grassed waterway. Trapezoidal on the left, parabolic on the right.

Roughness coefficient – selected by using the Manning roughness coefficient table. The choice of roughness coefficient must be appropriate for the section of channel being planned. Channel depth and width must be calculated for each change in channel condition.

Velocity – refer to the suggested maximum permissable velocities of flow table as design should not exceed these values.

Planning methodology – use the Manning formula (external link) and roughness coefficients to calculate waterway flow depth and width for peak flow. Correct method of calculating hydraulic radius must be used with the appropriate cross-sectional shape. In the case of a shallow trapezoidal cross-section, hydraulic radius in Manning’s formula may be substituted by average depth.

Capacity – sufficient to contain the peak flow run-off from a 20-year ARI (average recurrence interval) storm. Once design ARI is exceeded, the waterway will overflow. Greater capacity can only be built into the waterway by replanning for a greater ARI. This may be necessary where overflows from a planned waterway will cause other than superficial damage.

Vegetation cover — on waterway channels and banks to be annual or perennial grass pasture species, or a mixture of both. Dependent on soil type, clover or medic additions to the grass mix are encouraged. Seed at double pasture and fertiliser rates.

Outlets – shall be stable and of sufficient capacity to prevent ponding or erosion. The outlet can be into another vegetated channel or natural waterway.

Width – not to exceed 30 m without allowance for multiple or divided channels.

Channel cross fall between banks or levees – ideally to be zero. For up to 40 m distance, it is acceptable to have a maximum of 10 cm cross fall; however, this must be within design limits.

Levees – when required, to have a maintained 20 cm freeboard above design peak flow (Figure 2). Sideslope of levee adjacent to the flow to be no steeper than 2:1. Sideslope of levee outside of waterway to be no steeper than 6:1.

Diagram of a cross-section of a leveed grassed waterway showing the freeboard needed
Figure 2 Freeboard requirements for a leveed grassed waterway

Bank inlets – are incorporated in each levee sufficient to allow overland flows, outside the levee, to enter the waterway. Generally, inlets are not required where a grade bank system is installed in conjunction with the waterway. However, on steeply sloping land or where paddock run-off is excessive, additional inlets are recommended.

If there is no grade bank system, inlets are required along the levee at spacings no greater than that of grade banks for the equivalent slope.

Upslope opening of inlet has a freeboard of 20 cm above design peak flow.

Back to top

Legal and environmental aspects

Legal aspects and downstream properties

  • Waterways must not divert flows from one catchment to another catchment that would not naturally receive that flow.
  • Flow velocity must not be increased by the inappropriate use of additional freeboard to provide extra flow capacity.
  • Due care must be taken during construction and maintenance to stop the loss of disturbed material from the site.

Environmental aspects

  • Flows of poor quality water can degrade downstream channels, watercourses and wetlands.
  • Eroded material from poorly planned, constructed or maintained waterways, can reduce flow capacities when deposited in downstream channels.

Construction

  • Construct waterways with a grader or bulldozer.
  • Use appropriate survey techniques to peg the alignment and width of the waterway, as detailed on the plan. Survey cross-sections and cut and fill pegged as required.
  • Stockpile topsoil when filling or shaping, and re-spread over disturbed areas.
  • Use machinery weight to compact the fill or shape.
  • Construct levees from outside the channel, using appropriate techniques, resulting in the levees being compacted to the correct height including freeboard.
  • Survey bank inlet positions for correct spacings and positions. Set the ends of the inlet to eliminate back flow out of waterway.
  • Check level of the waterway channel surface to determine the accuracy of construction. Use levelling to confirm the levee freeboard.

Operation and maintenance

Grassed waterways greatly reduce the risk of water erosion – if they are effectively maintained!

  • Do not cultivate grassed waterways.
  • Maintain vegetation cover at 10–20 cm high.
  • Mow or periodically graze vegetation to maintain flow capacity.
  • Reconstruct damaged channel floors and levees to original specifications.
  • Do not use waterway as an access track or firebreak.
  • Control noxious weeds.

Back to top

Reference material

  • Bligh, KJ 1989, Soil conservation earthworks design manual, Department of Agriculture, Western Australia, Perth.
  • Clement, J Bennett, M, Kwaymullina, A & Gardner, A 2001, The law of landcare in Western Australia, 2nd edn, Environmental Defender’s Office WA (Inc), Perth.
  • Houghton, PD & Charman, PEV 1986, Glossary of terms used in soil conservation, Soil Conservation Service of New South Wales.
  • Hudson, N 1992, Soil conservation, BT Batsford Ltd., London, England.
  • Schwab, GO Fangmeier, D & Elliot, W 1995, Soil and water management systems, 4th edn, John Wiley and Sons Inc., Toronto, Canada.
  • Schwab, GO, Fangmeier, D, Elliot, W, & Frevert, R 1992, Soil and water conservation engineering, 4th edn, John Wiley and Sons Inc., Toronto, Canada.

Support and extension material

Contact information

John Firth